First 24 hours
Confirm safe access, essential systems, communication channels, emergency vendor response, and a single record custodian. Do not send teams into unsafe areas to complete documentation.
After a storm, boards and managers need a shared record of what is known, what is urgent, who can authorize work, and what proof will close each action.
Start with safety and official direction. Then document observed conditions, access limits, temporary measures, vendor instructions, costs, insurance communications, and resident updates in one controlled record.
Each entry should have a timestamp, source, decision owner, authority, next action, due date, and evidence of completion. Mark unverified information clearly. Keep personal and claim details in access-controlled records rather than a public board update.
Confirm safe access, essential systems, communication channels, emergency vendor response, and a single record custodian. Do not send teams into unsafe areas to complete documentation.
Document observed damage, obtain qualified assessments, preserve relevant evidence, notify the appropriate insurance contacts, and control emergency commitments.
Rank mitigation work, check scope and rates, track permits and inspections, update affected residents, and compare costs with available cash and funding.
Approve scope changes, verify completed work, reconcile claim and project records, retain warranties, communicate remaining restrictions, and assign lessons learned.
These prompts are operational examples. Set property-specific deadlines and owners using current conditions, governing documents, contracts, policies, and qualified advice.
26 items shown
| When and area | Decision | Evidence and owner | Escalate when |
|---|---|---|---|
| First 24 hoursSafety | Confirm site access and immediate hazards | Official clearance and dated site observationsOwner: Incident lead | Unsafe access or unverified clearance |
| First 24 hoursSafety | Secure damaged areas and restricted routes | Access map and barrier photographsOwner: Property manager | Public access reaches an unresolved hazard |
| First 24 hoursCommunication | Publish a verified status update | Approved message and delivery reportOwner: Communication lead | Conflicting or unverified instructions circulate |
| First 24 hoursUtilities | Confirm power water and communications status | Utility notices and system readingsOwner: Facilities lead | Life-safety or essential service remains unavailable |
| First 24 hoursRecords | Open a controlled incident record | Timestamped log and document indexOwner: Records custodian | Decisions occur outside the record |
| First 24 hoursVendors | Confirm emergency vendor availability | Call log and written mobilization termsOwner: Property manager | Critical vendor cannot respond |
| First 72 hoursSafety | Arrange qualified assessment of affected systems | Specialist findings and limitationsOwner: Board liaison | Structural or life-safety condition is uncertain |
| First 72 hoursDamage | Photograph affected assets before work begins | Location-tagged photo register and baselineOwner: Assessment lead | Conditions may change before documentation |
| First 72 hoursDamage | Separate observed damage from assumptions | Condition register and verification statusOwner: Assessment lead | Unverified cause is presented as fact |
| First 72 hoursInsurance | Notify broker or insurer under policy procedure | Notice confirmation and policy referenceOwner: Insurance liaison | Notice deadline or coverage question arises |
| First 72 hoursInsurance | Preserve relevant records and damaged items | Preservation log and professional directionOwner: Insurance liaison | Evidence may be discarded or altered |
| First 72 hoursFinance | Set emergency spending authority and controls | Delegation record and purchase logOwner: Treasurer | Commitment exceeds authorized limit |
| First weekOperations | Prioritize temporary mitigation and essential services | Risk-ranked work list and approvalsOwner: Incident lead | Delay increases damage or resident impact |
| First weekVendors | Confirm scope rates and exclusions before authorization | Written work order and rate scheduleOwner: Procurement lead | Work starts with unclear scope or cost |
| First weekProjects | Track permits inspections and professional sign-off | Permit register and inspection statusOwner: Project lead | Work proceeds without required approval |
| First weekCommunication | Issue a predictable update schedule | Message calendar and accessible channel listOwner: Communication lead | Residents lack a reliable status channel |
| First weekResidents | Record accessibility and relocation needs securely | Restricted needs log and referral recordOwner: Resident liaison | Essential accommodation remains unresolved |
| First weekFinance | Reconcile commitments invoices and cash outlook | Cost forecast and invoice evidenceOwner: Treasurer | Forecast gap or unsupported charge appears |
| RecoveryProjects | Approve scope changes through one register | Change request basis price and authorityOwner: Project lead | Unapproved change affects cost or schedule |
| RecoveryInsurance | Maintain claim correspondence and decision trail | Claim index and dated correspondenceOwner: Insurance liaison | Request or response deadline approaches |
| RecoveryGovernance | Record board decisions and delegated actions | Minutes resolutions and action registerOwner: Board secretary | Authority or decision rationale is unclear |
| RecoveryOperations | Verify repairs and service restoration | Inspection results and completion evidenceOwner: Facilities lead | Work is marked complete without verification |
| RecoveryFinance | Compare recovery costs with budget and funding | Actuals forecast and funding decisionOwner: Treasurer | Funding source or cash timing is uncertain |
| RecoveryRecords | Archive final reports warranties and approvals | Controlled closeout indexOwner: Records custodian | Key completion evidence is missing |
| CloseoutGovernance | Review open risks and lessons learned | After-action review and assigned actionsOwner: Board liaison | Recurring control gap has no owner |
| CloseoutCommunication | Confirm final status to affected groups | Approved closeout notice and delivery logOwner: Communication lead | Material restrictions remain unexplained |
A team finds standing water beside a condominium entry after authorities permit site access. The first log entry records the time, exact location, photographs, access restriction, and the person who observed it. The manager assigns a facilities lead to assess the drain and requests qualified input if the condition may affect electrical equipment or building safety.
Temporary mitigation receives its own authorization and cost record. A separate entry tracks the permanent repair proposal, insurer or broker notification when relevant, resident access message, inspection result, and final invoice. The board sees what is confirmed, what remains uncertain, and which decision is due next.
This is an illustrative workflow, not a report of a particular property or claim.
Download the CSV and add actual timestamps, site locations, verification status, authority references, due dates, cost commitments, document links, and closure evidence. Keep the working copy access controlled.
Use the emergency communications plan for message ownership and the board decision register for formal approvals.
This operational framework draws on the federal hurricane guidance at Ready.gov and the FEMA hurricane safety and recovery sheet. Local emergency management and public safety instructions take priority. Building safety, cause of damage, coverage, claim rights, restoration methods, and legal duties require the relevant qualified professionals.
The template does not establish a statutory deadline or replace a property-specific emergency plan, insurance policy, or professional assessment.
Safety, insurance, and permanent repairs move at different speeds.
The immediate safety log should identify hazards, access restrictions, temporary protection, and who cleared each area. The loss record should preserve condition evidence, dates, communications, costs, and insurer requests. The repair plan should define scope, qualified review, procurement, permits where applicable, funding, and acceptance. Link the three registers with a common event ID, but do not treat an insurer estimate as an approved construction scope.
Photograph conditions before cleanup when safe, preserve damaged materials when instructed, and keep receipts for emergency work. The insurance claim documentation guide details the evidence trail. Continue to update residents on access and service status through the emergency communication plan, even when coverage or final repair dates remain uncertain.