Capital project control tool

Make every project change a documented decision.

A change request should explain the field condition, scope, price, schedule effect, risk, authority, and proof of completion before it disappears into the next payment application.

By Published Updated

Quick answer

Use one numbered register from request to closeout.

Record the original contractual baseline, the observed reason for change, the proposed work, itemized cost, time effect, funding source, professional review, and written approval. Keep emergency stabilization identifiable from permanent work.

Do not equate an approved price with verified completion. Inspect quantities and quality, reconcile invoices and the schedule, and collect updated drawings, permits, warranties, and records before closing the item.

25 controlsFrom intake to closeout
8 stagesOne controlled register
1 ownerFor each open change
Decision sequence

Separate the question from the approval.

01

Describe

Capture the field condition with a unique ID, location, date, photographs, original contract reference, and the person who raised it.

02

Evaluate

Ask for a defined scope, itemized price, credits, schedule logic, permit implications, safety and quality review, and funding forecast.

03

Authorize

Confirm the decision maker, specialist recommendation, and written direction before nonemergency work begins.

04

Verify

Inspect the work, reconcile quantities and invoices, update the schedule and controlled drawings, and close the records gap.

Filterable control library

Find the next review point.

These controls are a management framework. The executed contract, governing documents, professional scope, and site conditions determine the actual process and authority.

25 items shown

25 change controls · version September 23, 2026
StageControlEvidence and ownerEscalate when
IntakeAssign a unique change request IDNumbered register and submission dateOwner: Project managerWork is directed outside the register
IntakeDescribe the observed conditionSite report and location photographsOwner: Field leadCondition is undocumented
IntakeIdentify who initiated the changeRequest and authority recordOwner: Project managerRequester lacks authority
IntakeSeparate emergency stabilization from permanent workSafety instruction and temporary scopeOwner: Owner representativeImmediate safety action is delayed
ScopeState the original contract requirementExecuted scope and drawing referenceOwner: Contract administratorBaseline requirement cannot be found
ScopeDescribe added deleted and changed workMarked-up scope and quantitiesOwner: Design professionalChange scope is ambiguous
ScopeRecord assumptions and exclusionsWritten proposal qualificationsOwner: Project managerMaterial exclusion is hidden
ScopeCheck affected permits and inspectionsPermit and inspection reviewOwner: Design professionalApproval path is unclear
ScopeAssess warranty and system interfacesManufacturer and specialist inputOwner: Facilities leadChange compromises existing coverage
PriceRequest itemized labor material equipment and markupPrice breakdownOwner: Cost reviewerLump sum lacks support
PriceCompare unit rates with contract termsRate schedule and quantity checkOwner: Contract administratorNew rate conflicts with agreement
PriceCheck credits for deleted workOriginal scope value and credit scheduleOwner: Cost reviewerDeleted scope is billed in full
PriceUpdate contingency and funding forecastCost-to-complete forecastOwner: TreasurerAvailable funding is uncertain
ScheduleQuantify time and sequencing effectUpdated schedule with logicOwner: Project managerDelay claim lacks critical-path basis
ScheduleReview impacts on residents and accessAccess plan and communication draftOwner: Property managerOccupied areas are affected without plan
RiskDocument safety and quality consequencesRisk review and inspection hold pointsOwner: Design professionalUnreviewed condition affects safety
RiskCheck insurance and bonding implicationsContract and coverage reviewOwner: Risk liaisonCoverage position is unclear
ApprovalConfirm decision authority and quorumDelegation and board recordOwner: Board secretaryWork is approved by the wrong role
ApprovalRecord professional recommendation and limitsWritten recommendationOwner: Owner representativeDecision relies on unverified assumption
ApprovalIssue written authorization before nonemergency workSigned change order or written directionOwner: Contract administratorWork starts without written authority
ExecutionUpdate drawings logs and site instructionsCurrent controlled documentsOwner: Project managerCrews use superseded direction
ExecutionVerify installed quantities and qualityInspection and measurement recordsOwner: Field leadPayment precedes verification
ExecutionReconcile invoice and schedule updatesPayment application and updated forecastOwner: TreasurerChange is billed twice or early
CloseoutCollect warranties permits and as-built changesCloseout indexOwner: Records custodianFinal documents omit the change
CloseoutRecord final cost schedule and lessons learnedApproved final register and variance explanationOwner: Owner representativeChange remains open after acceptance
Worked example

A concealed facade condition changes the repair scope.

During restoration, the contractor documents a condition that was not visible in the original survey. The owner representative gives the request an ID and preserves photographs and drawing references. A qualified design professional evaluates the condition and defines the required scope before the board considers cost or schedule.

The proposal separates added work from credits for deleted work and states unit rates, assumptions, permit implications, resident access effects, and time impact. The authorized party records a written decision. At completion, field measurements, inspection evidence, the payment application, updated drawings, and warranty records close the same register entry.

The scenario is illustrative; the contract and project professionals control the actual technical and approval process.

Open template

Keep the approved baseline visible.

Download the CSV and add actual request IDs, contract references, proposed and approved amounts, contingency balance, schedule days, approval dates, inspection results, invoice links, and closeout status.

Use the capital project oversight guide for the wider project sequence and the closeout checklist for final acceptance.

Download

CSV25 controls · spreadsheet-readyOperational template · updated September 23, 2026
Scope and judgment

Use the contract and qualified project team.

Change orders can affect safety, design, permitting, insurance, funding, and contractual rights. This register helps leaders organize evidence and decisions; it does not replace the engineer, architect, contractor, lawyer, insurer, or other qualified adviser responsible for a particular issue.

← Return to all property insights

Working method

Test the complete effect of a proposed change

A change is more than its quoted price.

Compare the proposed work with the signed scope and drawings, then record the cause, quantities, labor and material basis, exclusions, markup, and whether another contractor or warranty is affected. Ask for a revised schedule showing critical milestones, access restrictions, and inspection dependencies. If a change saves money, document what performance or warranty is surrendered.

For example, a wall repair discovered after demolition may require temporary protection before the final detail is designed. Record temporary work separately from permanent work and define the authorization limit for each. Keep field direction, board approval, contract amendment, and payment certification linked, so no invoice becomes the first evidence of an expanded scope.