Describe
Capture the field condition with a unique ID, location, date, photographs, original contract reference, and the person who raised it.
A change request should explain the field condition, scope, price, schedule effect, risk, authority, and proof of completion before it disappears into the next payment application.
Record the original contractual baseline, the observed reason for change, the proposed work, itemized cost, time effect, funding source, professional review, and written approval. Keep emergency stabilization identifiable from permanent work.
Do not equate an approved price with verified completion. Inspect quantities and quality, reconcile invoices and the schedule, and collect updated drawings, permits, warranties, and records before closing the item.
Capture the field condition with a unique ID, location, date, photographs, original contract reference, and the person who raised it.
Ask for a defined scope, itemized price, credits, schedule logic, permit implications, safety and quality review, and funding forecast.
Confirm the decision maker, specialist recommendation, and written direction before nonemergency work begins.
Inspect the work, reconcile quantities and invoices, update the schedule and controlled drawings, and close the records gap.
These controls are a management framework. The executed contract, governing documents, professional scope, and site conditions determine the actual process and authority.
25 items shown
| Stage | Control | Evidence and owner | Escalate when |
|---|---|---|---|
| Intake | Assign a unique change request ID | Numbered register and submission dateOwner: Project manager | Work is directed outside the register |
| Intake | Describe the observed condition | Site report and location photographsOwner: Field lead | Condition is undocumented |
| Intake | Identify who initiated the change | Request and authority recordOwner: Project manager | Requester lacks authority |
| Intake | Separate emergency stabilization from permanent work | Safety instruction and temporary scopeOwner: Owner representative | Immediate safety action is delayed |
| Scope | State the original contract requirement | Executed scope and drawing referenceOwner: Contract administrator | Baseline requirement cannot be found |
| Scope | Describe added deleted and changed work | Marked-up scope and quantitiesOwner: Design professional | Change scope is ambiguous |
| Scope | Record assumptions and exclusions | Written proposal qualificationsOwner: Project manager | Material exclusion is hidden |
| Scope | Check affected permits and inspections | Permit and inspection reviewOwner: Design professional | Approval path is unclear |
| Scope | Assess warranty and system interfaces | Manufacturer and specialist inputOwner: Facilities lead | Change compromises existing coverage |
| Price | Request itemized labor material equipment and markup | Price breakdownOwner: Cost reviewer | Lump sum lacks support |
| Price | Compare unit rates with contract terms | Rate schedule and quantity checkOwner: Contract administrator | New rate conflicts with agreement |
| Price | Check credits for deleted work | Original scope value and credit scheduleOwner: Cost reviewer | Deleted scope is billed in full |
| Price | Update contingency and funding forecast | Cost-to-complete forecastOwner: Treasurer | Available funding is uncertain |
| Schedule | Quantify time and sequencing effect | Updated schedule with logicOwner: Project manager | Delay claim lacks critical-path basis |
| Schedule | Review impacts on residents and access | Access plan and communication draftOwner: Property manager | Occupied areas are affected without plan |
| Risk | Document safety and quality consequences | Risk review and inspection hold pointsOwner: Design professional | Unreviewed condition affects safety |
| Risk | Check insurance and bonding implications | Contract and coverage reviewOwner: Risk liaison | Coverage position is unclear |
| Approval | Confirm decision authority and quorum | Delegation and board recordOwner: Board secretary | Work is approved by the wrong role |
| Approval | Record professional recommendation and limits | Written recommendationOwner: Owner representative | Decision relies on unverified assumption |
| Approval | Issue written authorization before nonemergency work | Signed change order or written directionOwner: Contract administrator | Work starts without written authority |
| Execution | Update drawings logs and site instructions | Current controlled documentsOwner: Project manager | Crews use superseded direction |
| Execution | Verify installed quantities and quality | Inspection and measurement recordsOwner: Field lead | Payment precedes verification |
| Execution | Reconcile invoice and schedule updates | Payment application and updated forecastOwner: Treasurer | Change is billed twice or early |
| Closeout | Collect warranties permits and as-built changes | Closeout indexOwner: Records custodian | Final documents omit the change |
| Closeout | Record final cost schedule and lessons learned | Approved final register and variance explanationOwner: Owner representative | Change remains open after acceptance |
During restoration, the contractor documents a condition that was not visible in the original survey. The owner representative gives the request an ID and preserves photographs and drawing references. A qualified design professional evaluates the condition and defines the required scope before the board considers cost or schedule.
The proposal separates added work from credits for deleted work and states unit rates, assumptions, permit implications, resident access effects, and time impact. The authorized party records a written decision. At completion, field measurements, inspection evidence, the payment application, updated drawings, and warranty records close the same register entry.
The scenario is illustrative; the contract and project professionals control the actual technical and approval process.
Download the CSV and add actual request IDs, contract references, proposed and approved amounts, contingency balance, schedule days, approval dates, inspection results, invoice links, and closeout status.
Use the capital project oversight guide for the wider project sequence and the closeout checklist for final acceptance.
Change orders can affect safety, design, permitting, insurance, funding, and contractual rights. This register helps leaders organize evidence and decisions; it does not replace the engineer, architect, contractor, lawyer, insurer, or other qualified adviser responsible for a particular issue.
A change is more than its quoted price.
Compare the proposed work with the signed scope and drawings, then record the cause, quantities, labor and material basis, exclusions, markup, and whether another contractor or warranty is affected. Ask for a revised schedule showing critical milestones, access restrictions, and inspection dependencies. If a change saves money, document what performance or warranty is surrendered.
For example, a wall repair discovered after demolition may require temporary protection before the final detail is designed. Record temporary work separately from permanent work and define the authorization limit for each. Keep field direction, board approval, contract amendment, and payment certification linked, so no invoice becomes the first evidence of an expanded scope.